Have been conducted 72-hour testing of installations
Published by: 04.11.2016

At the end of October fully complete the implementation of construction works in kindergarten Kindergarten No10 “Slantchitze” and Municipal Social Complex.  By Order of the Mayor of Dobrich Municipality have been conducted 72-hours tests in both buildings of the new mounted heating systems, according to Spatial Planing Act.

There have been conducted 72-hours tests, as follows

-      In Kindergarten №10 - replacement of the boiler of gas and liquid fuel, construction of a new substation and internal heating installation. Held a 72-hour test in the operating conditions of the building in the period from 10.00h on 31.10.2016 to 10.00h of 03.11.2016.

-      In the Complex for social services - optimizing the heating system by replacing boilers and installation of new heating system. Held a 72-hour test in the operating conditions of the building in the period from 10.00h on 26.10.2016 to 10.00h of 29.10.2016.

During the tests any irregularities or shortcomings have been found of the normal operation of heating systems.

Next steps are preparation of the necessary documentation from construction supervision and further commissioning of the buildings’ installations, according to Spatial planning act.